Civil Works
Access road clearing works in progress
Excavator arrived at site and clearing of access road from Power house to Intake is in progress
PCC works in progress at SP 166,167,168,169&170 of PL.
PCC works in progress at AB41 lower bed of PL.
Formworks in progress at AB42 lower bed of PL.
Foundation excavation work in progress at SP 179,180,181,182,183,184 and 185, AB44&45.
Reinforcement works in progress at AB42 lower bed of PL.
Formworks and Concreting work in progress at SP 171,172,173&174
Formworks and Concreting work in progress at SP
←